Wednesday, 2 May 2012

Train Refurbishment

If you are thinking about refurbishing your rolling stock, here some valuable lessons, learned through bitter experience:
  • Always have a clear and fixed remit agreed with the operators before going ahead with the design;
  • Never assume new stuff will fit into all the old trains. Even if it is specially designed, it probably won’t;
  • Avoid messing with wiring unless you strip it all out and replace it;
  • Every train/vehicle should be jointly tested and surveyed before acceptance by the contractor. All defects to be noted and agreed by both parties for inclusion in the work (or not) as required;
  • Always assume you will find things you didn’t expect when you strip – you will, sometimes even when you're getting near the end of the job;
  • Always expect things that are not supposed to be touched will be and will get damaged as a result;
  • Always allow a long learning curve for the first few trains;
  • Avoid changes in design or requirements mid-contract. It will be very expensive;
  • Have some your own experienced staff working with the contractor’s team, on site, for the full duration of the contract, including the design phase. They can offer valuable help, build up a rapport with the contractor and keep an eye on things;
  • Upon completion, jointly check and test every vehicle and then couple into a train and test again before acceptance;
  • Always expect it to cost more than you estimated;
  • Always expect it to take longer than you estimated;
  • Don’t go for the lowest bid because it’s the lowest. It will cost more in the end;
  • Work with your contractor rather than against him. Openness and co-operation will be cheaper for both of you.
There are certainly more lessons I could add but these are the most pertinent. I offer these because, almost 20 years after I was first involved in train refurbishment, these mistakes are still being made. I heard recently that, a year into a 2010 train refurbishment project, all the above lessons had been ignored, the contractor was forced into bankruptcy and the operator was left with a huge bill and a partly refurbished fleet that he now has to re-tender for, so he can get it all working again.

Saturday, 3 March 2012

A Wrong Turn

A lady driver, aged 85, took a wrong turn at a level crossing at Basingstoke in England on January 26th  2012, when she drove onto the railway track and drove for 80 metres before she realised something wasn't quite right. She had a 20 year old male in the car with her. Apparently she was looking for the station car parking area. She's lucky she and the car didn't light up the area by touching the electric conductor rail that the line has.

One has to wonder how someone who can do that kind of thing has survived to that age. And as for her passenger, where was his brain.  Perhaps it was a family member....

Of course the railway was shut down for two hours and thousands of passengers had their journeys disrupted while the mess was sorted out.  I hope she will be prosecuted for endangering the lives of railway passengers.

Thursday, 1 March 2012

More Railway Contracts in Saudi Arabia


The Arab News reports that Finance Minister, Ibrahim Al-Assaf, on Saturday 25th February 2012 signed three contacts worth SR2.34 billion with Saudi Arabian Railway (SAR) to implement a number of projects related to the North-South Railway. Starting from Riyadh, the 2,750-km railway reaches up to the northern border town of Hudaitha passing by Sudair, Qassim, Hail and Al-Jouf. It also links the phosphate and bauxite mines in Jelamaid and Baitha with industrial plants in Ras Al-Khair, Jubail and Dammam. 

The new contracts were signed to establish five passenger stations, a maintenance complex in Naeeriya, 36 remote maintenance workshops, plus a technical support office and housing units for maintenance staff. Al-Rashid Trading & Contracting won the first contract worth SR1.57 billion to establish five passenger stations in Majmaa, Qassim, Hail, Al-Jouf and Qurayat. Each station will cost SR314.4 million. It is said that the project will be completed in an ambitious 24 months. 

The SR495.7 million maintenance complex project was won by Yabi Markazi Co., and an official statement carried by the Saudi Press Agency said that it would be completed within 18 months. It will provide maintenance for locomotives and carriages as well as for track. The project includes fuel supply depots. 

Sulaiman Al-Qudaibi & Sons won a third contract valued at SR271.58 million to establish 36 small maintenance workshops along the railway including 15 for the maintenance of track and communication systems, 11 hostels to house workers and eight administrative buildings. Speaking to reporters after the signing ceremony, Al-Assaf said the North-South Railway project was progressing well. “Last year we conducted experimental operation of the railway for transporting phosphate from Jelamaid to Ras Al-Khair,” he said, adding that it can transport up to 12,500 tons of phosphate in one trip. 

The government has given priority to the North-South Railway considering its role in industrial development. It would ferry minerals from mines in the north and central zones at Jelamaid and Zubairah to processing plants at Ras Al-Khair in the east. Sponsored by the Public Investment Fund, the rail line is integral to planned phosphate and bauxite mining projects in the north of the country that will link up with processing plants and smelters on the Gulf coast. It is of strategic importance to the national economy as the processing of phosphates, which exists in commercial quantities, will place the Kingdom second internationally in exports of the mineral, besides accommodating fertilizer industry technology. It will also increase oil, agricultural and industrial products transportation, as well as goods and passengers.

It is interesting that Saudi Arabia has led the railway development programme in the Middle East. They are only too well aware of the limitations of their oil reserves and they know that, eventually, it will dry up. Positioning themselves for the Kingdom's future development, post oil, they are looking to ore mining and processing as one of the replacement industries.  The building of the railway to get the ore from the mines in the north to the ports in the south east has been a priority for the government over that last few years.